Project Timeline

The timeline below offers a broad overview of the Hampstead Manor project, including proposed construction and refurbishment schedules. Visit our news and updates page for more details of current and upcoming works or to download the most recent local community newsletter.

2016
 
Apr
Construct Hoarding
 
Apr
Commence Soft Strip and Asbestos Removal
 
Jul
Commence Hard Demo
 
Oct
Commence Piling
 
2017
 
Jan
Commence Basement Excavation
 
Jan
Commence Refurb Fit Out
 
Apr
Commence New Build Structures
 
Aug
1st Refurb Handover
 
Aug
Commence New Build Fit Out
 
2018
 
Apr
1st New Build Handover
 
Oct
Last New Build Handover
 
Nov
Last Refurb Handover
 